Tip:
To address the stipulation that that at least two of the projects 1, 3, 5, 6 must be undertaken, make Sum of B12, D12, F12, G12 >= 2
To address the stipulation that Project 4 cannot be undertaken unless both projects 1 & 3 are also undertaken make E12<= B12 & E12<=D12
Model
| Brooks Development | |||||||
| Parameters | |||||||
| Project | 1 | 2 | 3 | 4 | 5 | 6 | |
| Net Present Value ($ Millions) | $15 | $5 | $13 | $14 | $20 | $9 | Budget |
| Expenditure Required ($ Millions) | $90 | $34 | $81 | $70 | $114 | $50 | $220 |
| Model | |||||||
| Project | 1 | 2 | 3 | 4 | 5 | 6 | |
| Invest | |||||||
| Cost | $0.00 | ||||||
| Total NPV | $0.00 | ||||||
| Projects 1,3,5,6 |